Ten Distributions

Describe each uncertain duration, impact or cost with one of ten distributions, and see its shape as you enter it.

How It Works

  1. Choose a Shape

    Triangular, Beta PERT, Split-Triangular, Uniform, Trigen, Normal, LogNormal, Discrete, Cumulative or Single Point.

  2. Enter the Numbers

    Three points, a mean and standard deviation, percentiles or a table of points, depending on the shape.

  3. Check the Preview

    The panel draws the shape. For a cost element it also shows the mean and a P-value you can move. The run itself is sampled on our servers.

Details

What You Get

  • Ten distributions, including Trigen, Split-Triangular, Discrete and Cumulative.
  • Trigen and Split-Triangular take low and high percentiles, and the bounds are worked out from them.
  • Discrete takes values with weights. Cumulative takes values with cumulative probabilities.
  • The same shapes are used for risk impacts, duration uncertainty and cost elements.

Limits and Conditions

  • Beta PERT uses a fixed shape factor of 4.
  • Normal and LogNormal cannot be truncated. Normal stops at zero.
  • Poisson, Weibull, Gamma and Exponential are not available in the QRA engine.

Duration Uncertainty

Put a range on activity durations in bands, by WBS level or by chosen activities. An activity’s own three-point estimate wins where it has one.

  • Bands in any of the ten distributions, as a percentage or in days.
  • An activity’s own estimate overrides the band.
  • Three-point estimates can come in with the schedule import.
  • AI can draft bands from the schedule.

Try RiskForesight for 14 Days.